Scope of Works
We delivered enabling works, groundworks, structural foundations and associated road and infrastructure works for the multi-storey car park.
- Site preparation: Temporary access to the island site, cut-and-fill earthworks and ground preparation for the future Building 123 development.
- Highway works: Section 278 works, including a new roundabout and reconfigured entrance and exit roads.
- Drainage and utilities: Installation of drainage and service ducts.
- Foundations: Construction of car park foundations and bases for road lighting and CCTV columns.
- External works: Footpaths, paved areas, and hard and soft landscaping.
Project Gallery