Scope of Works
We delivered enabling works, groundworks and substructure works for the first of two NHS multi-storey car parks, maintaining hospital traffic flow throughout construction.
Site preparation: Reprofiling site levels and installing a sheet pile retaining wall along the northern boundary.
Piling support: Construction of a piling platform for Vinci's piling contractor, followed by pile breaking.
Substructure: Construction of pile caps, retaining walls and foundations to support the steel-framed car park.
Drainage and infrastructure: Drainage installation, with a planned return to complete external works, utilities and site access roads.
The car park will provide an initial 100 EV charging bays, 24 motorcycle spaces and 50 accessible spaces.